Boiler light-up test for 1200 MW thermal plant achieved
October 28, 2015
Bhopal
Hindustan Power Projects Pvt Ltd (HPPPL) achieved a critical milestone towards commissioning its 1200 MW phase 1 (600 x 2 units) at Anuppur thermal project in Madhya Pradesh by successfully conducting the boiler light-up test for the second unit.
“The successful conduct of boiler light-up test signifies the readiness of the boiler for power generation process and the company has started the work for steam blowing and synchronization of the unit well within the scheduled timeline,” Hindustan Power Chairman, Ratul Puri told PTI.

“The country needs a robust growth in our energy sector hence the objective of the organization is to deliver a state-of-the-art thermal project capable of sustainably generating high efficiencies,” Puri said.
“The improved performance would also mean increased power availability. We are now at the doorsteps of commissioning 1200 MW which would play a critical role in addressing energy gap in the power deficient region,” he said.
The company is setting up a 2520 MW thermal power plant in phases at village Jaithari, district Anuppur.
The plant has achieved critical milestones in terms of land acquisition, coal and water linkage, securing various statutory and other clearances ahead of schedule.
PTI
Recent Stories
- Diwali Food Safety Drive: AMC Seals Two Units, Fines Four Outlets ₹40,000
- HDFC Bank Gets Govt Nod to Offer Deposits Under Capital Gains Accounts Scheme
- GSSSB Announces Recruitment for 1,237 Class-3 Posts; Applications Open on November 5
- AMC to Hike Parking Fees; Proposed New Rates Here
- Mumbai Mayor Ritu Tawde Meets Gujarat CM Bhupendra Patel
- Holiday Inn Resort to Come Up in Sasan Gir