Power cables, towers shifted successfully, Civil construction to start soon: NHSRCL
January 16, 2021
Gandhinagar: National High Speed Rail Corporation Limited (NHSRCL) on Friday said, ‘shifting of 220 KV electrical cables and towers (Jambuva – Karamsad line) has been completed successfully in Gujarat. This work involved dismantling three 220 KV suspension type towers, erection of four new towers, stringing 1.412 km of electrical cable line and dismantling of 1.351 km of existing line.’ NHSRCL further said, ‘Work is completed successfully now and we are well on our way preparing site for civil construction commencement soon.’ DeshGujarat