Over 76,000 Segments to be cast for 16 km tunnel for Bullet Train Project
May 21, 2024
Mumbai: A 21-kilometer tunnel is under construction between the Bandra Kurla Complex and Shilphata for the Mumbai-Ahmedabad Bullet Train Project. Of the total length, 16 kilometers will be excavated using three Tunnel Boring Machines (TBMs), while the remaining 5 kilometers will be constructed using the New Austrian Tunnelling Method (NATM).
To construct the 16-kilometer section with TBMs, 76,940 segments will be cast to form 7,441 rings. Special ring segments are being cast for the tunnel lining, each ring comprising nine curved segments and one key segment, with each segment being 2 meters wide and 0.5 meters thick.
High-strength M70 grade concrete is being used to ensure superior structural integrity and long-term durability. The casting and stacking yard, covering an area of 98,898 sqm (9.9 hectares) in Mahape, Thane district, Maharashtra, is currently being commissioned. The yard will feature nine sets of moulds, each containing ten pieces. Four sets of these moulds are already being installed on-site.
The yard is equipped with various cranes, gantries, and machines to automate and mechanize the casting operations, ensuring high-quality assurance during the casting and stacking of the segments. Additionally, the facility will include casting sheds, a stacking area, a batching plant, and a steam curing area.
Recent Stories
- Union Cabinet approves development of National Maritime Heritage Complex (NMHC) in Lothal, Gujarat
- More about migrant Muslims who raped a minor Hindu girl in Vadodara during Navratri night
- Ukai dam generated 27.49 crore power units in monsoon 2024
- Rain may dampen Garba mood in these parts of Gujarat; IMD forecasts rainfall until Oct 12
- 3 govt employees held in Rs. 9 crore water supply scam in Navsari
- Only Surat district receives rain in the last 24 hours
- 7 new pay-and-park facilities to come up in Ahmedabad; AMC issues tender