Western Railway Deploys Three 500-Tonne Cranes to Build 3 Bridges in Gujarat

Western Railway Deploys Three 500-Tonne Cranes to Build 3 Bridges in Gujarat

Morbi: Western Railway’s Ahmedabad division has strengthened flood protection along vulnerable railway sections in Gujarat’s Morbi district by completing a series of engineering works. The upgrades include the construction of three bridges during a single railway block using three heavy-duty cranes with a combined lifting capacity of 1,500 tonnes.

The work was carried out along the Maliya Miyana–Vadharva section of the Viramgam–Samakhiali railway line. The upgrades also include around 3.7 km of protective walls and 12 additional drainage structures to improve water flow during heavy rainfall and floods.

The division said the works are aimed at protecting railway tracks, embankments and bridges from erosion and flood damage while reducing disruptions to passenger and freight services.

Three bridges built during a single block

The railway undertook work on bridges 147/D, 147/E and 147/F between Vadharva and Maliya Miyana, at chainage 699/16 to 699/24. Three cranes, each with a lifting capacity of 500 tonnes, were deployed to construct the bridges during a single block, enabling the work to be completed through a coordinated heavy-machinery operation.

The new drainage structures will provide additional passage for floodwater, reducing the risk of water flowing over tracks, eroding embankments or washing away soil beneath the railway line.

Additional drainage openings have also been constructed near level crossings 95 and 97, while improvements have been carried out at other vulnerable stretches in the area.

3.7 km of protection walls and improved drainage

The division has constructed around 3.7 km of protective walls at vulnerable locations to prevent soil erosion and strengthen railway embankments against strong water currents.

A total of 12 additional drainage openings have been developed across vulnerable sections, including Vadharva–Maliya Miyana, Maliya Miyana–Dahisara and Maliya Miyana–Surabari.

At bridge No. 155 near the Ahmedabad end of Maliya Miyana yard, a damaged drainage arrangement comprising three 600-mm pipes has been replaced with a box bridge. The upgrade is expected to allow more water to flow beneath the tracks and reduce pressure during flooding.

Flood-prone stretch has faced repeated disruptions

Maliya Miyana is vulnerable to flooding during heavy rainfall and water releases from the Machchhu-2 and Machchhu-3 dams. Floods in 1979, 2017 and August 2024 damaged transport infrastructure in the region.

During the August 2024 floods, railway tracks were submerged and soil beneath the tracks was washed away at several locations along the Samakhiali–Maliya Miyana, Maliya Miyana–Dhrangadhra and Maliya Miyana–Wankaner sections, disrupting train operations.

The latest engineering upgrades cover nearly seven km of vulnerable railway stretches and are intended to reduce the risk of similar damage during future extreme weather events.

Critical freight connectivity to Kandla and Mundra protected

Maliya Miyana is an important railway junction connecting Kutch and Saurashtra with Ahmedabad and other parts of the country. The railway network through the junction is also crucial for freight movement to and from major ports, including Kandla and Mundra.

Flood-related disruptions on these routes can affect freight movement, industrial activity and supply chains, apart from passenger services. The new drainage and protection works are expected to improve the reliability of this critical rail network.

The division has also stocked quarry dust, boulders and railway ballast in the area as a monsoon emergency reserve to enable quicker repairs and restoration in case of damage.

DRM Ved Prakash said passenger safety, uninterrupted train operations and protection of railway infrastructure from natural disasters remain top priorities. He said the improvements were aimed not only at repairing past flood damage but also at building stronger infrastructure capable of withstanding future extreme weather.

He also praised the engineering teams for completing the three-bridge construction during a single block, calling it an example of technical capability, planning and coordinated execution. DeshGujarat