Platform 2 and 3 at Surat railway station to shut for 98 days; 83 trains to halt at Udhna
December 03, 2024
Surat: As part of the ongoing work to upgrade Surat Railway Station into an MMTH (Multi-Modal Transport Hub), platforms 2 and 3 will be closed from December 7th. As a result, more than half of the trains currently stationed at Surat will be shifted to Udhna station. Around 15% of the trains will be moved to the Udhna terminal.
These platforms will remain closed for approximately 98 days. Of the 180 trains that currently halt at Surat Station, 83 will be shifted to Udhna, while 66 will continue to be handled at Surat. Additionally, 31 trains that either start or terminate at Surat will be redirected to Udhna. Premium trains will also have their platforms changed at Surat. The time gap between trains will be reduced during this period.
The work on platforms 2 and 3 will involve tasks such as the construction of COP foundations, roof foundations, lifts, columns, and beams. It is also noteworthy that the redevelopment of platform 4 has been completed at Surat Railway Station, but due to issues with road access and parking in the eastern area, platform 4 remains closed for now. DeshGujarat
Related Stories
Surat Railway Station platforms 2 & 3 closure extended till March 31; Diversion to Udhna to continue
Chain Pulling on the Rise near Surat railway station as 206 trains stop only at Udhana
Western Railway revises halts for these trains from Surat Railway Station to Udhna
Recent Stories
- Rahul Gandhi to be on Gujarat visit on April 15–16
- Bridge City Surat likely to get one more bridge on April 18th
- Former MLA Mahesh Vasava quits BJP
- Work begins on 1.3-km tunnel in Poshina for Taranga Hill–Ambaji–Abu Road rail project
- AUDA to repair 3 bridges on SP Ring Road
- Gabbar Hill darshan, Parikrama route, Ropeway to remain shut from April 15-17
- Western Railway to run Udhna–Danapur Unreserved Special Train