97.17% railway line electrification done in Gujarat; 3187 km of 3972 km electrified under Modi in Centre

Gandhinagar: India celebrated 100 years of its first-ever electric train on Monday. Over the past century, the nation has electrified 64,547 km of its total broad gauge railway network. Of this, 3,972 km have been electrified in Gujarat, covering over 97% of the state’s broad gauge railway network as of 3rd February 2025.

As per the latest figures on December 31, 2024, Gujarat has a total of 4,087 km of broad gauge railway lines, out of which 3,972 km have been electrified, leaving only 115 km without electrification. The electrification of railway line makes it possible to operate electric engine run trains. Apart from overhead electric line, substations are also required at places to make this possible. In a latest, the Ahmedabad Himmatnagar Udaipur railway line electrification project is completed.

Notably, as of April 1, 2014, only 785 km were electrified in Gujarat, according to government data. This means that around 3,187 km—nearly 80% of the state’s broad gauge network—has been electrified since Prime Minister Narendra Modi took office in 2014.

Similarly, across India, the railways are progressing rapidly toward 100% electrification. Out of the total 66,504 km of broad gauge network, 97.06%, or 64,547 route kilometers (rkm), has been electrified. Only 1,957 km of broad gauge track remains to be electrified nationwide, which is expected to be completed soon. Since April 2022, an average of 48 km of railway routes has been electrified per month.

During the Modi government’s tenure, several railway electrification projects were completed across Gujarat. Key routes that have been electrified include Ahmedabad-Palanpur, Ahmedabad-Viramgam-Surendranagar-Rajkot, and Rajkot-Okha with Kanalus-Sikka. Other major routes include Mahesana-Viramgam-Dhrangadhra-Samakhiyali, Samakhiyali-Gandhidham-Adipur with Kandla Port-Mundra Port, Adipur-New Bhuj, Palanpur-Samakhiyali, and Surendranagar-Dhrangadhra. Additionally, electrification was completed on the Wankaner-Dahinsara-Maliya Miyana, Dhola-Sihor-Palitana with Sihor-Bhavnagar, Rajula-Mahuva, Jhund-Kharaghoda, Mahesana-Patan-Bhildi, and Rajkot-Gondal-Jetalsar-Veraval routes. Other important sections include Nadiad-Modasa, Kanalus-Wansjaliya-Porbandar, Surendranagar-Pipavav Port, Mahesana-Varetha, Dhasa-Jetalsar, Vishwamitri-Dabhoi-Ekta Nagar, Anand-Khambhat, and Ahmedabad-Mahesana.

Meanwhile, electrification work is still in progress on the Asarva-Himmatnagar and Bhimnath-Moraiya sections. DeshGujarat

No.  State Total broad gauge
RKM
Electrified broad gauge
RKM upto 31.12.2024
Balance RKM % Electrified
1 Andhra Pradesh 3841 3841 0 100.00%
2 Bihar 3855 3855 0 100.00%
3 Chandigarh 16 16 0 100.00%
4 Chhattisgarh 1297 1297 0 100.00%
5 Delhi 183 183 0 100.00%
6 Haryana 1780 1780 0 100.00%
7 Himachal Pradesh 67 67 0 100.00%
8 J&K 396 396 0 100.00%
9 Jharkhand 2577 2577 0 100.00%
10 Kerala 1046 1046 0 100.00%
11 Madhya Pradesh 4962 4962 0 100.00%
12 Maharashtra 5815 5815 0 100.00%
13 Meghalaya 9 9 0 100.00%
14 Nagaland 11 11 0 100.00%
15 Odisha 2918 2918 0 100.00%
16 Puducherry 21 21 0 100.00%
17 Punjab 2288 2288 0 100.00%
18 Telangana 1923 1923 0 100.00%
19 Uttar Pradesh 8546 8546 0 100.00%
20 Uttarakhand 347 347 0 100.00%
21 West Bengal 4032 3977 55 98.64%
22 Rajasthan 5961 5805 156 97.38%
23 Gujarat 4087 3972 115 97.19%
24 Karnataka 3615 3488 127 96.49%
25 Tamil Nadu 3898 3659 239 93.87%
26 Goa 186 164 22 88.17%
27 Tripura 267 153 114 57.30%
28 Assam 2533 1431 1102 56.49%
29 Arunachal Pradesh 12 0 12 0.00%
30 Manipur 13 0 13 0.00%
31 Mizoram 2 0 2 0.00%
32 Sikkim 0 0 0 0.00%
Total 66504 64547 1957 97.06%