Western Railway announces mega blocks in Geratpur–Vadodara section; several trains affected
May 07, 2025
Vadodara: To facilitate the re-girdering work on Bridge No. 624, located between Vasad and Ranoli stations in the Geratpur–Vadodara section, Western Railway has scheduled several mega blocks. As a result, select train services will either be fully or partially cancelled, while others will face schedule changes.
Train Cancellations and Partial Cancellations:
-
Train No. 19035 Vadodara – Ahmedabad Intercity Express will remain cancelled on 7th, 11th, 14th, 18th, 21st, and 28th May, and 4th and 8th June 2025.
-
Train No. 19036 Ahmedabad – Vadodara Intercity Express will also be cancelled on the same dates.
-
Train No. 12930 Vadodara – Valsad Intercity Express will not run on 7th, 11th, 14th, 18th, 21st, and 28th May, and 4th and 8th June 2025.
-
Train No. 22960 Jamnagar – Vadodara Intercity Express will be partially cancelled between Ahmedabad and Vadodara on 7th, 11th, 14th, 18th, 21st, and 28th May, and 4th and 8th June 2025.
Rescheduled and Regulated Trains:
-
Train No. 20902 Gandhinagar Capital – Mumbai Central Vande Bharat Express will depart 1 hour late on 11th, 18th May, and 6th June 2025.
-
Train No. 12010 Ahmedabad – Mumbai Central Shatabdi Express will be delayed by 30 minutes on 7th, 14th, 21st, 28th May, and 4th June 2025.
-
Train No. 14807 Jodhpur – Dadar Express will be regulated by 1 hour 40 minutes on 11th, 18th May, and 6th June 2025.
-
Train No. 12477 Jamnagar – Shri Mata Vaishno Devi Katra Express will be delayed by 50 minutes on 7th, 14th, 21st, 28th May, and 4th June 2025.
-
Train No. 16533 Bhagat Ki Kothi – KSR Bengaluru Express will be regulated by 55 minutes on 7th, 14th, 21st, 28th May, and 4th June 2025.
-
Train No. 20626 Bhagat Ki Kothi – Chennai Central Superfast Express will be delayed by 40 minutes on 11th, 14th, 18th, 21st, and 28th May, and 4th and 8th June 2025.
-
Train No. 16209 Ajmer – Mysuru Express will be regulated by 55 minutes on 11th, 18th May, and 8th June 2025. DeshGujarat
Recent Stories
- VUDA Clears ₹801 Crore Budget, ₹50 Crore Allotted for Ring Road Project
- SC Orders Status Quo in Bhadra Parisar Case; Stays Reinstatement of Street Vendors
- Hindu Minor Lured Into Love Trap, Fake Aadhaar Used to Book Hotel Room; Three Held in Ahmedabad
- Delivery of 10 New Trainsets for Ahmedabad Metro Likely to Commence from June 2026
- AMC Announces Ahmedabad Innovation and Startup Policy 2026, ₹250 Crore Fund Planned