SMC slaps ₹3.32 crore fine on contractor of Dumas Sea-Face project; threatens blacklisting
December 16, 2025
Surat: Given the delays in the opening of Zone 1 of the much-anticipated Dumas Sea-Face Development Project, the Surat Municipal Corporation (SMC) has imposed a fine of Rs 3.32 crore on the contractor, M/s M P Babariya, and issued a notice threatening blacklisting. Jayesh A. Dalal Planning & Engineering Services Pvt Ltd, the project management consultancy, has also come under scrutiny.
Zone-1 (Urban Zone), Package-1 of the Sea-Face project, which includes recreational and tourism development works such as an eco-tourism park on Dumas Beach, was handed over to the contractor in March 2024. Despite repeated written and verbal reminders, progress remained slow.
A review meeting on October 9, chaired by the Mayor, Municipal Commissioner, and Standing Committee Chairman, instructed that all work, except the portion obstructed by the GETCO line, be completed by December 15.
However, during a site visit on December 8, Commissioner Shalini Agarwal observed that large portions of the promenade, event ground, sculptures, horticulture, and amenities building interiors and exteriors remained incomplete. The SMC warned that continued delays could damage the project’s credibility and image, leading to the issuance of notices demanding explanations, which has now been followed by the hefty fine.
Related Stories
Recent Stories
- Surat Diamond Industrialist Dhiru Rmanai Freed After Three Months in Mali; Reports Say €4 Million Ransom Paid
- Cube Highways Trust Announces Price Band for Initial Public Offering; Issue Opens on July 22, 2026
- 60 Indians Deported from UAE Arrive in Surat Amid Immigration Crackdown
- AC waiting room at Vadodara Railway Station commercialized
- Live : Ahmedabad Rath Yatra 2026
- Vadodara Hit-and-Run: CCTV Shows Speeding Car Ramming Bike, Three MSU Students Injured