Latest Progress Update of Ahmedabad–Mumbai Bullet Train Project
January 19, 2026
Ahmedabad: The National High Speed Rail Corporation Limited (NHSRCL) has shared the latest progress update on the country’s first high-speed rail corridor, popularly known as the Mumbai–Ahmedabad Bullet Train Project.
As per the update issued on January 11, the total length of the corridor stands at 508 km, comprising 352 km in Gujarat and Dadra and Nagar Haveli, and 156 km in Maharashtra.
The project includes 12 thematically designed Bullet Train stations — Sabarmati, Ahmedabad, Anand, Vadodara, Bharuch, Surat, Bilimora and Vapi in Gujarat, and Boisar, Virar, Thane and Mumbai in Maharashtra.
According to NHSRCL, out of the total 508 km corridor, 332 km of viaduct construction and 415 km of pier work have been completed. A total of 17 river bridges have also been completed, including five pre-stressed concrete (PSC) bridges and 12 steel bridges.
More than 4.9 lakh noise barriers have been installed along a 245-km stretch of the alignment. Additionally, 292 track kilometres (146 route kilometres) of reinforced concrete (RC) track bed construction have been completed.
The installation of overhead equipment (OHE) infrastructure is progressing steadily, with around 4,800 OHE masts erected, covering approximately 111 route kilometres of the mainline viaduct.
In Maharashtra’s Palghar district, breakthrough has been achieved in the first of the seven mountain tunnels. Excavation work on the remaining six tunnels is currently underway.
Further, 5 km of NATM tunnel has been excavated out of the total 21 km tunnel section between Bandra Kurla Complex (BKC) and Shilphata in Maharashtra.
Construction work on the rolling stock depots at Surat and Ahmedabad is progressing, while superstructure work at all stations in Gujarat has reached an advanced stage.
In Maharashtra, work has commenced on all three elevated stations, and base slab casting at the Mumbai underground station is currently in progress. DeshGujarat
Leave a Reply
Recent Stories
- Rain Activity to Gradually Increase Across Gujarat; South Gujarat to Receive Showers Throughout Week
- Watch | Lion lifts Pilgrim's Bag at Shetrunjay Hill in Palitana
- Senior Gujarat Police Officers to Stay Overnight in Border Villages
- Domestic LPG Cylinder Price Hiked by ₹29; New Rates Effective from Midnight
- Four Workers Die of Suspected Toxic Gas Exposure While Cleaning ETP Tank in Surat
- AI, Drone Technology, EV Repair, Solar Energy, 3D Printing Among Key New Courses Introduced in ITIs of Gujarat
