Latest Progress Update of Ahmedabad–Mumbai Bullet Train Project
January 19, 2026
Ahmedabad: The National High Speed Rail Corporation Limited (NHSRCL) has shared the latest progress update on the country’s first high-speed rail corridor, popularly known as the Mumbai–Ahmedabad Bullet Train Project.
As per the update issued on January 11, the total length of the corridor stands at 508 km, comprising 352 km in Gujarat and Dadra and Nagar Haveli, and 156 km in Maharashtra.
The project includes 12 thematically designed Bullet Train stations — Sabarmati, Ahmedabad, Anand, Vadodara, Bharuch, Surat, Bilimora and Vapi in Gujarat, and Boisar, Virar, Thane and Mumbai in Maharashtra.
According to NHSRCL, out of the total 508 km corridor, 332 km of viaduct construction and 415 km of pier work have been completed. A total of 17 river bridges have also been completed, including five pre-stressed concrete (PSC) bridges and 12 steel bridges.
More than 4.9 lakh noise barriers have been installed along a 245-km stretch of the alignment. Additionally, 292 track kilometres (146 route kilometres) of reinforced concrete (RC) track bed construction have been completed.
The installation of overhead equipment (OHE) infrastructure is progressing steadily, with around 4,800 OHE masts erected, covering approximately 111 route kilometres of the mainline viaduct.
In Maharashtra’s Palghar district, breakthrough has been achieved in the first of the seven mountain tunnels. Excavation work on the remaining six tunnels is currently underway.
Further, 5 km of NATM tunnel has been excavated out of the total 21 km tunnel section between Bandra Kurla Complex (BKC) and Shilphata in Maharashtra.
Construction work on the rolling stock depots at Surat and Ahmedabad is progressing, while superstructure work at all stations in Gujarat has reached an advanced stage.
In Maharashtra, work has commenced on all three elevated stations, and base slab casting at the Mumbai underground station is currently in progress. DeshGujarat
Recent Stories
- Customs Nabs Travel Agent in Ahmedabad Airport Gold Smuggling Case
- Surat New Civil Hospital Opens 12-Bed Brain Stroke ICU
- Gujarat Vandana Museum at Ekta Nagar to come up at a Cost of Rs. 900 Crore
- Rohit Sharma to Captain Mumbai Indians
- Surat Heritage Walk to begin Nov 29, Cover 12 Historic Sites every Sunday
- Sabarmati Riverfront to Host Ironman 70.3 Triathlon in Ahmedabad
- Western Railway to Add Extra Coaches to Rajdhani, Shatabdi, 5 Other Trains
- Western Railway to Run 2 Special Trains from Ahmedabad to South India
- Ahmedabad-Mumbai Karnavati Express Terminal to Be Temporarily Shifted
- Gujarat Tops India in Compostable Plastics Manufacturing with 62 Units
- Gujarat Draft Electoral Roll 2027 Published, State Has 4.48 Crore+ Registered Voters
