30-Day Block at Surat Railway Station, Some Trains to Operate from Udhna
March 27, 2026
Surat: The modernization work at Surat railway station has reached a crucial stage. As part of the station redevelopment project, the railways will carry out the launching of a through-roof shed between platforms 2–3 and 4. For this purpose, the railway administration has issued a Traffic Working Order (TWO) for 30 days, which will affect several long-distance trains operating from Surat.
According to railway officials, the work will begin on March 30, 2026, and will continue for 30 consecutive days.
During this period, for the convenience of passengers and to facilitate the work, some trains will be operated from Udhna station instead of Surat.
Changes in train operations
Train No. 12935 Bandra Terminus–Surat Intercity Express: From March 30 to April 28, 2026, the train will terminate at Udhna instead of Surat and return from there.
Train No. 20925 Surat–Amravati Superfast Express: From April 2 to April 26, 2026, the train will depart from Udhna instead of Surat on Thursdays, Fridays, and Sundays.
Train No. 20926 Amravati–Surat Superfast Express: From March 30 to April 27, 2026, the train will run only up to Udhna on Mondays, Fridays, and Saturdays and will remain cancelled between Udhna and Surat.
Railway authorities said the temporary changes are necessary to complete the redevelopment work safely and on schedule. DeshGujarat
Leave a Reply
Recent Stories
- 3 Killed, Others Injured After Truck Rams Parked Car on Delhi-Mumbai Expressway in Vadodara
- Ambaji Shaktipeeth Corridor Project: Phase-2 Anti-Encroachment Drive Begins
- Stray Dog Menace: 7-Year-Old Boy Attacked in Surat
- Rajkot Businessman Loses Rs 29 Lakh in Fake SNITCH Franchise Scam
- Schools Reopen Across Gujarat After 35-Day Summer Vacation; New Academic Year 2026-27 Begins
- Vadodara Police Bust Fake Call Centre Targeting Foreign Nationals, Four Held
