Narmada Dam’s height increasing work to finish before schedule
August 01, 2016
Ahmedabad: Construction work to increase the height of Narmada dam at Kevadia in Gujarat’s Narmada district to 138.72 metres from existing 121.92 metres will be completed by December this year, nine months ahead of the schedule, a top government official said today.
In June 2014, soon after Narendra Modi took over as the Prime Minister, the Narmada Control Authority (NCA) had approved the proposal to raise the height of the dam by putting up radial gates on it. The construction work began in October, 2014.
“The scheduled time to increase the height of the Narmada dam to 138.7 metres was September next year. Instead of that, we have set ourselves a target to finish the work by December 2016,” chief engineer of Sardar Sarovar Narmada Nigam Limited (SSNNL), P C Vyas, told PTI.
Even after completion, however, the newly-constructed gates will remain open keeping the operational height of the dam at the existing 121.92 metres, until rehabilitation and resettlement (R&R) works for dam-displaced persons is completed.
The NCA will have to give a go-ahead to operationalise the gates after it is convinced that all R&R work is completed, as per the orders of the Supreme Court.
The state-run SSNNL is the implementing agency of the Narmada dam project.
“Construction of piers and bridge have been completed, and all thirty radial gates have been installed on the top of the dam. Only finishing and auxiliary works are left which we will complete by December,” Vyas said.
He said construction work was expedited to advance the actual target date with both the SSNNL management and construction company making special efforts on their part to finish the work at the earliest possible.
Infrastructure major Jaypee Associates is involved in the construction of the dam.
“Coordination between the management headed by SSNNL CMD S S Rathore and the contractor helped expedite the work.
Engineers worked hard day and night and contractor put extra resources for this,” Vyas said.
PTI
Related Stories
A historic day for Gujarat; closure of 30 gates on Narmada dam initiated today morning
Have a look at big benefits closure of Narmada dam gates will bring to Gujarat
Sardar Sarovar Narmada dam overflows for the first time in this season
Permission for closure of Narmada dam gates likely after March 2017: Anandiben
Installation of gates over Narmada dam to be completed 8 months ahead of schedule:CM
Narmada main dam works to be completed by September 2017
Narmada dam: 690 meter long bridge construction work over
Narmada dam expected to achieve full height as per schedule in 2016:CM
Process of installation of gates over Narmada dam begins
Installation of gates over Narmada dam likely to begin in October
Installation of gates over Narmada dam likely to begin in October
Recent Stories
- Passenger held at Ahmedabad airport with ₹16 lakh worth of gold hidden in almond packet
- RBI cancels licence of a cooperative bank in Ahmedabad
- One held in Ahmedabad for selling urea fertilizer; 1188 bags seized
- MEA Jaishankar visits National Maritime Heritage Complex, Lothal
- ACB Gujarat nabs Dy Mamlatdar, aide in bribe case in decoy trap
- Locals object to public preaching by missionaries in Ukai; video goes viral
- Illegal properties of bootleggers bulldozed in Ahmedabad