Long-pending completion of Patan’s new bus port to take another 6 months
December 09, 2023
Patan: The construction of the new bus port, valued at Rs. 70 crore in the city, has been ongoing for six years. With over 80% of the work complete, the bus port is expected to be ready for operation in another 6 months.
The RCC construction of two floors of basement parking, five floors above ground, and 22 bus platforms has been completed. Flooring and finishing work have commenced, and to expedite the project, an additional labor force of 50 is being deployed.
In 2018, this project was initiated to replace the old bus station in Patan city with a new and modern bus station. Despite facing setbacks due to the COVID-19 pandemic, the work has resumed, with 50 laborers currently engaged. Another 50 laborers from Bhuj will join the workforce, with the goal of completing all remaining tasks within six months, as disclosed by S.B. Trivedi, Deputy Engineer of the Mehsana Construction Department.
The current progress indicates that the two-storey underground parking, accommodating 1000 cars and 2800 bikes, is ready. Construction above ground level has reached five floors, and 22 platform forms are prepared. Only the remaining work, including plastering and finishing-style painting, is left to be completed, according to infrastructure sources. – DeshGujarat
Recent Stories
- Amit Shah to launch ₹1,024 crore projects in Ahmedabad during Diwali visit
- Kankaria Lakefront to Get Two Made-in-India Toy Trains
- Congress Conspiring to Create Bangladesh-Like Puppet Govt in India: Union Minister in Surat
- CNG Car Blast in Vadodara; 5 Injured as Debris Flies 200 Metres
- Kajal Baraiya Murder: Faizal Sentenced to Life Imprisonment by Bhavnagar Court
- Sakkarbaug Zoo to Exchange Four Asiatic Lions for Six Capuchin Monkeys