5th PSC Bridge Completed for Bullet Train Project in Gujarat

Surat: A 260 m long PSC bridge over National Expressway- 4 near Kosamba, Surat district is completed on 22nd February 2025 for Mumbai-Ahmedabad Bullet Train Project.

The project is crossing over National Expressway- 4 between Delhi & Mumbai (passing through Rajasthan & Gujarat) near Kosamba at Surat district, Gujarat through elevated viaduct.

The bridge features 104 precast segments with four spans of configuration 50m + 80m + 80m + 50m and was built using the Balanced Cantilever Method, which is ideal for larger spans.

The newly completed bridge is located in between Surat and Bharuch Bullet Train stations.

National Expressway-4 is under construction Expressway between Delhi & Mumbai. The construction was meticulously planned to ensure the safety of both vehicles and workers while maintaining uninterrupted traffic flow and minimizing public inconvenience.

Details of completed PSC bridges in Gujarat:

Sr. No. Length of bridge (in m) Span Configuration Bullet Train Stations District Location Completed on
5th PSC Bridge 260 Four spans of configuration 50m + 80m + 80m + 50m Between Surat & Bharuch Surat National Expressway – 4 22nd February 2025
4th PSC Bridge 210 Four spans of configuration 40m + 65m + 65m + 40m Between Anand & Ahmedabad Kheda NH-48 9th January 2025
3rd PSC Bridge 210 Four spans of configuration 40m + 65m + 65m + 40m Between Vapi & Bilimora Valsad NH-48 2nd January 2025
2nd PSC Bridge 210 Four spans of configuration 40m + 65m + 65m + 40m Between Surat & Bilimora Navsari NH-48 1st October 2024
1st PSC Bridge 260 Four spans of configuration 50m + 80m + 80m + 50m Between Surat & Bilimora Navsari NH-48 18th August 2024

These details were shared by National High Speech Railway Corporation Ltd (NHSRCL) in a formal press release. DeshGujarat