Tata Power Restarts 4,150 MW Mundra Plant After 9-Month Shutdown
April 02, 2026
Mumbai: Tata Power has restarted operations at its 4,150 MW Mundra thermal power plant after a shutdown lasting nearly nine months, the company said in a regulatory filing on Wednesday.
The plant, run by its subsidiary Coastal Gujarat Power Ltd, had been non-operational since July 2, 2025, resulting in continued financial losses during the downtime.
Located in Kutch, Gujarat, the Mundra facility is among the country’s largest coal-fired power stations, with five units of 800 MW each. It supplies electricity to several states, including Gujarat, Maharashtra, Rajasthan, Punjab, and Haryana.
Operations have resumed following the signing of supplementary power purchase agreements (PPAs), notably with Gujarat Urja Vikas Nigam Ltd.
The Gujarat cabinet had cleared the revised agreement last month, enabling the plant’s revival, while similar arrangements are being negotiated with other states.
The development comes amid efforts by the government to boost power generation to meet rising electricity demand. DeshGujarat
Related Stories
Recent Stories
- Bhat - Koteshwar Road Junction to Get Capsule Traffic System
- Income Tax Dept Conducts Searches in Surat
- Gujarat ATS Nabs Suspected Jaish-e-Mohammed Terrorist in Vadodara, Seizes AK-47
- Ahmedabad Metro: Sabarmati Railway Metro Station to Open on Nov 28
- Pakwan Circle Capsule Traffic System on SG Highway Suspended
- Four Cheetahs from Kenya to Arrive in Gujarat by Year-End
- AMC to Hold Terrarium Workshop Ahead of Ahmedabad Flower Show 2027
- AMC Sets Deadline for Repairs at Community Halls Amid Wedding Season
- Stray Cattle Menace: AMC to Review Performance of 19 Cattle-Catching Teams
- AMC Standing Committee Returns Maktampura Gymnasium Operation Tender
- HYROX Gujarat Kicks Off, Draws 6000 Athletes from India and Abroad