Udhna – Jalgaon double line project in final phase; Surat to benefit from it
February 22, 2018
Surat: A 306 km long Udhna-Jalgaon double line work is now in final phase. Entire 276 km line barring just 30 km on Dondaicha – Nandurbar stretch is ready. The double line project which was started in year 2009 is likely to complete within this financial year. The first train will be on track next week on this route for trial run. With completion of this line 35% of total 125 trains that pass through Surat railway station will be shifted to Udhna. They will be mostly the goods train. They will use the new double line track from Udhna. This will make it possible to utilize Surat railway station for other new trains.
DeshGujarat
Related Stories
Udhna Railway Station to undergo upgradation at a cost of ₹ 199.02 crore
Surat - Jalgaon Railway Project: Supreme Court stays demolition of 5,000 slum units
Surat getting three new trains, new double track line to Jalgaon
Doubling of Udhna - Jalgaon railway track over
Recent Stories
- One held in Surat for circulating anti-Hindu pamphlets aimed at defaming son-in-law
- Ensure Effortless GST Compliance and Simplify Your Business with Vyapar App’s Billing Software
- Meru Cabs by Mahindra now available at Ahmedabad Airport
- SpiceJet adds another Ahmedabad-Jaipur direct flight
- Man in Mahesana comes alive after "his" cremation
- Development of Central Park starts in GIFT City; Phase 1 likely to be ready by 2025
- Surat trader to give sarees to women voting early in Maharashtra polls