Rajkot district collector reviews progress of under construction Hirasar Airport works
August 19, 2021
Rajkot: Rajkot Collector Arun Mahesh Babu visited the site of New Greenfield International Airport under construction at Hirasar village near Rajkot and instructed for timely completion of the project.
The works on run-way, boundary wall, land flattening, parking taxi track and taxi link are completed by 50 %, 60 %, 55 %, 95 % and 100 % respectively.
The Collector instructed Mamlatdar and Prant officers to complete the shifting of Juna Hirasar, Limakotadi and Doslidhu villages that are within the boundary wall with collaboration of locals in. He also instructed the officials of respective departments regarding Internal Road Diversion, Electricity Wiring Shift, Wind-mill shifting and other works.
Hirasar airport will be spread across 1030 hectares. PM Narendrabhai Modi had performed its foundation stone laying. All the construction work except the terminal building are likely to be finished in year 2022. Terminal Building works are likely to be completed by January 2023. Airport Officials informed that security towers will be set-up on the boundary line in the operational area of 11.5 km and non-operational area of 14.5 km.
Related Stories
35 properties coming in the way of Hirasar Airport’s approach road to be acquired
Hirasar airport project in Rajkot: Over 80% earth work, Runway and other pavement works completed
Recent Stories
- Complaint filed against convent teacher, wife for alleged religious conversion video in Navsari
- ED, CGST dept to probe Rs. 6,000 crore scam by BZ Group; police seize luxury cars
- IndiGo announces daily Surat-Kolkata flight from Dec 27
- GSRTC launches Ahmedabad Airport - Dhordo AC Volvo bus service
- Schedule Caste members hold rally against Vadgam Congress MLA Jignesh in Mahisagar
- Gujarat govt transfers 37 GAS senior officers
- Gujarat ACB nabs 2 govt-licensed surveyors in Palanpur for demanding ₹1 lakh bribe