Ahmedabad-Mumbai Bullet Train Project: Another breakthrough achieved
August 29, 2024
Silvassa: Another steel bridge of 100 m length has been launched for the Mumbai-Ahmedabad Bullet Train Project on 25.08.2024 near Silvassa in Dadra and Nagar Haveli.
This 1464 MT of steel bridge of 14.6 m in height and 14.3 m in width has been fabricated at the workshop in Trichy, Tamil Nadu and was transported on trailers to the site for installation.
A temporary launching nose spanning 84 meters and weighing 600 MT was connected with the main bridge for launching, to avoid any intermediate support. Additional temporary members were also installed to strengthen the bridge during launching.
100 m long ‘Make in India’ steel bridge launched in Silvassa, Dadra & Nagar Haveli for the Mumbai-Ahmedabad Bullet Train Project. This 1464 MT bridge, fabricated in Tamil Nadu and completed with precision, marks the fourth of 28 bridges, paving the way for high-speed connectivity pic.twitter.com/R6ZqYqbgE4
— NHSRCL (@nhsrcl) August 26, 2024
Total of 27,500 nos. of HSFG (High-strength friction grip) bolts were utilised to connect the components of launching nose and approximately 55,250 nos. of Tor-Shear Type High Strength (TTHS) bolts with C5 system painting and elastomeric bearings, were utilized for the main bridge.
The steel bridge along with launching nose were assembled near the site at a height of 14.5 m from the ground on temporary trestles and was pulled with automatic mechanism of 2 number of semi-automatic jacks, each of capacity of 250 ton using mac-alloy bars.
The Bullet Train project is being executed meticulously, maintaining the utmost standards of safety and engineering excellence. Leveraging Japanese expertise, India is increasingly utilizing its own technical and material resources to build infrastructure under the “Make in India” initiative. The steel bridge for the Bullet Train Project is a major example of this effort.
This is the fourth out of the 28 steel bridges, completed for the Bullet Train corridor. The details are as follows:
Number | Location | Date of launching | Length of the steel bridge | Weight of the steel bridge |
---|---|---|---|---|
1 | Across National Highway 53, Surat, Gujarat | 03/10/2023 | 70 m | 673 MT |
2 | Over Vadodara-Ahmedabad main line of Indian Railways, near Nadiad, Gujarat | 14/04/2024 | 100 m | 1486 MT |
3 | Over Delhi-Mumbai National Expressway, near Vadodara, Gujarat | 23/06/2024 | 130 m | 3000 MT |
4 | Near Silvassa in Dadra & Nagar Haveli | 25/08/2024 | 100 m | 1464 MT |
Recent Stories
- Schedule Caste members hold rally against Vadgam Congress MLA Jignesh in Mahisagar
- Gujarat govt transfers 37 GAS senior officers
- Gujarat ACB nabs 2 govt-licensed surveyors in Palanpur for demanding ₹1 lakh bribe
- Valsad-Bhagat Ki Kothi & Bandra Terminus-Barmer to run as superfast trains
- All special trains of Western Railway to run with regular train numbers from Jan 1, 2025
- Centre approves 2 tourism projects worth ₹151.06 crore in Gujarat under SASCI scheme
- Gujarat ATS arrests one from Dwarka for spying for Pakistani agents