Surat Metro Project Achieves Landmark as 8.5 km Viaduct Completed, Trials Begin
March 29, 2026
Surat: The Surat Metro Rail Project has reached a key milestone with the completion of an 8.5 km elevated viaduct between Dream City and Althan Tenement stations. Trial runs of metro trains on this stretch have commenced, according to the Gujarat Metro Rail Corporation(GMRC).
Officials stated that approximately 500 hours of trial operations will be conducted as part of system testing. The track-laying work on the route has been completed, along with the installation of the third rail system required for traction power.
Surat Metro Project Achieves Landmark as 8.5 km Viaduct Completed, Trials Begin ; Surtis flood social media with videos as the first glimpses of moving metro train spark excitement for a faster, modern commute https://t.co/dciASfUcdu pic.twitter.com/rEkSpcoOKo
— DeshGujarat (@DeshGujarat) March 29, 2026
Structural work for all seven stations along this corridor has also been completed. Finishing work, including entry and exit points, is currently underway.
Safety and operational readiness will be assessed through inspections by the Research Designs and Standards Organisation (RDSO) and the Commissioner of Metro Railway Safety (CMRS). Following these evaluations and approvals, the corridor will be considered for public operations.
The Surat Metro project is expected to contribute to urban transport capacity by providing an additional public transit option in the city. DeshGujarat
Leave a Reply
Related Stories
First Metro Trainset Arrives in Surat; Trial Runs Likely Soon
Gujarat Govt Orders 24 Trainsets for Under-Construction Surat Metro Rail Project
Surat Metro marks major milestone with tunnel breakthrough at Chowk Bazaar
Surat Metro Project: 96% Work Complete on Majura Gate - Dream City Route of Corridor-1
Major milestone for Surat Metro as downline tunnel completes at Chowk Bazaar
Recent Stories
- Rajkot Airport Gets Yatri Udan Cafe, Flybrary and Kids Zone
- PM Narendra Modi’s diplomacy a global garba: Actress Twinkle Khanna’s viral witty post
- 118 community kitchens operational in Surat region; Sanghavi reviews gas supply, workers arrangements
- Meals for 10,000 Pilgrims Daily, No LPG, No Firewood: Inside Gujarat’s Largest Biogas-Powered Mega Kitchen
- PM Modi to Launch Tourism Projects Worth Rs. 67 Crore in North Gujarat