Installation of gates over Narmada dam likely to begin in October
June 28, 2015
Bharuch
Installation of gates over Narmada dam is likely to begin on October 15 at Sardar Sarovar site at Kevadia colony in Gujarat.
Out of 29 piers, block number 42, 45, 47, 48, 49 and 50 these six blocks have reached top height of 144.5 meter. Other piers are in range of 133 to 143 meter height at present. Construction work is going on war foot basis to take them to ultimate height by July 15.
One all of them reach 144.5 meter height, construction of bridge will kick off atop them.
In total 30 gates are to be installed. Each of 23 gates will be in measurement of 55 by 60 ft while 7 gates will be in size of 60 by 60 ft. Installation work is likely to begin on 15 October.
– DeshGujarat
Related Stories
How final raising of Sardar Sarovar Dam cleared by Narmada Control Authority; an official note
Gujarat govt welcomes Supreme Court verdict on Sardar Sarovar project oustees, terms it historic
Narmada Dam's height increasing work to finish before schedule
Recent Stories
- Gujarat ACB nabs 2 govt-licensed surveyors in Palanpur for demanding ₹1 lakh bribe
- Valsad-Bhagat Ki Kothi & Bandra Terminus-Barmer to run as superfast trains
- All special trains of Western Railway to run with regular train numbers from Jan 1, 2025
- Centre approves 2 tourism projects worth ₹151.06 crore in Gujarat under SASCI scheme
- Gujarat ATS arrests one from Dwarka for spying for Pakistani agents
- Centre gives GI tag to Gujarat's handicraft 'Gharchola', bringing state's total GI tags to 27
- 20 judge positions vacant in Gujarat High Court, 535 vacancies in district & subordinate courts