Process of installation of gates over Narmada dam begins
October 07, 2015
Bharuch
The process of installation of gates over Narmada dam in Gujarat has kicked off. The works are likely to complete by March 2017.
Construction of 23 out of total 28 piers has completed upto top height of 144.5 meter, while rest 6 piers have achieved 142.3 to 144 meter height. By 20th of October, all 29 piers will achieve full height of 144.5 meter.
As piers work is nearly complete, the final task of installation of gates over the dam has started. It may take 18 months period to complete this task. As the BJP is ruling party in all concerned states including Gujarat, Maharashtra, Madhya Pradesh and Rajasthan, and the party is also ruling in center, the task is likely to complete by March 2017 without any further obstruction.
The government has spent about Rs 110 crore to achieve 144 meter height.
– DeshGujarat
Related Stories
How final raising of Sardar Sarovar Dam cleared by Narmada Control Authority; an official note
A historic day for Gujarat; closure of 30 gates on Narmada dam initiated today morning
Gujarat govt welcomes Supreme Court verdict on Sardar Sarovar project oustees, terms it historic
Narmada Dam's height increasing work to finish before schedule
Narmada dam expected to achieve full height as per schedule in 2016:CM
Recent Stories
- Bus from Gujarat to Ayodhya meets with accident; 50 injured
- PM Modi meets Padma Bhushan Jain Acharya Ratnasundersurishwarji Maharaj
- Update on work in progress on Vadodara-Godhra section of Delhi-Mumbai Expressway
- Portion of Ashram Road near Sabarmati Gandhi Ashram to shut permenently from Nov 9; details of alternate routes and parking
- A lucky car given Samadhi with last rites ceremony as per Hindu customs in rural Amreli
- CR Patil attacks Congress, National Conference over J&K Assembly's Article 370 resolution
- Three-day tribal trade fair begins in Navsari