Power cables, towers shifted successfully, Civil construction to start soon: NHSRCL
January 16, 2021
Gandhinagar: National High Speed Rail Corporation Limited (NHSRCL) on Friday said, ‘shifting of 220 KV electrical cables and towers (Jambuva – Karamsad line) has been completed successfully in Gujarat. This work involved dismantling three 220 KV suspension type towers, erection of four new towers, stringing 1.412 km of electrical cable line and dismantling of 1.351 km of existing line.’ NHSRCL further said, ‘Work is completed successfully now and we are well on our way preparing site for civil construction commencement soon.’ DeshGujarat
Related Stories
NHSRCL casts first full height pier on bullet train corridor near Vapi in Gujarat
Bullet train project: NHSRCL awards India’s largest infra contract in 35 days; construction starts for C-4 package
Bullet Train Project: L&T starts soil testing, ground surveys in Gujarat
First phase of bullet train project likely to be completed in Gujarat due to lack of 80 per cent land acquisition in Maharashtra
L&T awarded another mega contract to build bullet train project in Gujarat
Recent Stories
- Fake IAS officer held
- Cyclists hit by overspeeding SUV on SG Highway based overbridge
- Gujarat govt to form AI Task Force
- Khambhat police book 31 for attacking police personnel
- BJP wins Vav assembly by-election in Banaskantha
- Progress update of Vadodara - Dahod - MP Border section of Delhi-Mumbai Expressway
- Thaltej Gam Metro Station ready; likely to open in December 2024