Mumbai – Ahmedabad Bullet Train Project: 430 km Piers, 341 km Girder Work Completed: Centre
March 26, 2026
New Delhi: The Mumbai–Ahmedabad High Speed Rail (MAHSR) project, India’s first bullet train corridor, is progressing steadily with major civil works completed across large sections of the route, Union Minister of Railways Ashwini Vaishnaw informed the Lok Sabha.
Sharing the details of the project in a reply to a question, the Minister said that the 508-km-long Mumbai–Ahmedabad High Speed Rail project passes through Gujarat, Maharashtra and the Union Territory of Dadra & Nagar Haveli, with 12 stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati.
According to the latest status update, the entire land measuring 1,389.5 hectares has been acquired, all statutory clearances have been obtained, and 1,651 utilities have been shifted for the project. He said that delays in land acquisition in Maharashtra affected progress until 2021, but acquisition picked up in 2022, allowing construction to accelerate.
Major construction progress
The government said substantial work has been completed on key structural components of the corridor.
- Piers completed: 430 km
- Girder work: 341 km
- Track bed: 174 km
- Overhead equipment (OHE) masts: 153 km
Station construction status
Work on several stations in Gujarat has reached advanced stages.
- Sabarmati: Foundation completed; platform slab, roof structure and finishing work in progress
- Ahmedabad: Structural work completed; finishing work underway
- Vadodara: Foundation completed; structural and finishing works in progress
- Bharuch: Structural work completed; finishing work in progress
- Boisar: Foundation in advanced stage; structural work started
- BKC (Mumbai): Underground station; foundation almost complete and base slab work started
- Work is also in progress at Anand/Nadiad, Surat, Bilimora, Vapi, Virar and Thane stations.
River bridges under construction
Construction of multiple river bridges along the corridor is underway, with several already completed.
Bridges over Meshwa, Vishwamitri, Kim and Mindhola rivers have been completed, while major bridges over Narmada, Mahi, Tapi and Vaitarna rivers are at advanced stages of construction.
Work on the Sabarmati river bridge has completed the sub-structure, with superstructure work in progress.
Under-sea tunnel work underway
The project also includes a 21-km under-sea tunnel in Maharashtra, one of the most complex parts of the corridor.
So far, 4.8 km of tunnel between Ghansoli and Shilphata has been completed, and further tunnelling work is in progress.
Officials said the project has gained momentum after land acquisition issues were resolved and construction is now progressing simultaneously at multiple locations across Gujarat and Maharashtra. DeshGujarat
Leave a Reply
Recent Stories
- Akota Bridge in Vadodara to remain shut for 14 days for Bullet Train Work
- Ahmedabad to Host India vs Sri Lanka ODI Match; Rajkot Set for T20 Clash in 2026 Home Season
- Ahmedabad to Host India vs Australia 5th Test of Border - Gavaskar Trophy
- Western Railway Extends Trips of Several Gujarat-Passing Special Trains
- Western Railway’s Rajkot Division Runs First Long-Haul Mega Freight Train, Covers 306 km
