Morbi Bridge Collapse: 22 of the 49 cables were corroded reveals SIT
February 20, 2023
Morbi: A preliminary report submitted by a Special Investigation Team on the Morbi suspension bridge collapse in Gujarat in October 2022, revealed that 22 of the 49 cables were corroded and wires appeared to be broken before the collapse.
“22 of the 49 cables were corroded which indicates that those wires may already be broken before the incident. The remaining 27 wires recently broke,” the report said.
The report also highlighted anomalies in the renovation and repair of the bridge, including improper testing of the main cable and vertical suspenders, welding of old suspenders with new ones, and the installation of a new deck that increased the weight of the bridge. The report also alleged that repair works were carried out by a “non-competent authority”.
The SIT report recommended that periodic audits of public structures be conducted, a register maintained for all such structures, and a proper SOP be developed. It also recommended that competent authorities periodically inspect any structure used by the public. The report pointed out insufficient security to prevent public damage and unrestricted movement on the bridge due to a lack of restrictions on the number of people accessing the bridge and the sale of tickets. DeshGujarat
Related Stories
Granting Bail to Jaysukh Patel is the discretion of HC: Gujarat Govt in court
Morbi Bridge Collapse: SIT submits 5,000-page report in Gujarat HC
Jaysukh Patel seeks interim bail to pay compensation to Morbi bridge collapse victims
Morbi Bridge Collapse Case: Gujarat HC orders Oreva to pay interim compensation of Rs 10 lakh to kin of each victim
Recent Stories
- Stray bull attacks man in Bhachau, Kutch; CCTV footage surfaces
- In pictures: Upcoming Five-Star Hyatt Hotel at GIFT City, Gujarat
- Ahmedabad girl jumps from building after being blackmailed with intimate video; two booked
- Gujarat gets widespread rain on Saturday; Dwarka tops with 4.45 inches
- No RTO visit needed: Gujarat launches faceless learning license system
- Western Railway announces block on July 6; several Gujarat-passing trains to be affected
- IMD forecasts heavy rains in these parts of Gujarat till July 11 | Weather | मौसम | હવામાન