Update on work in progress on Dahod-Gujarat-MP Border section of Delhi-Mumbai Expressway
November 22, 2024
Dahod: The construction of the Delhi-Mumbai Expressway is ongoing, with packages 26 to 31 falling under the Dahod to Vadodara segment. In previous updates, we discussed packages 27 to 31. In this latest update, we share the most recent information from vloggers and on-site footage regarding Package 26, which stretches from Bhimpura village (Dahod district) to the state border between Gujarat and Madhya Pradesh. Based on the visuals, it appears that this last package in Gujarat is likely to take over a year to complete.
Package 26 is approximately 30 km long, starting at Bhimpura village in Dahod district and ending near the Anas river at the Gujarat-MP state border. At the beginning of the package, a village road crosses, and the overpass construction is pending. As we proceed ahead, a long viaduct is being constructed as a river lies in the path of the expressway. On one side of the viaduct, girder erection work is complete, while on the other side, pier construction work is underway. Moving ahead, hill-cutting work is being carried out in the hilly region, though most of the work is still pending. After crossing the hill, bitumen laying is happening in small patches (around 1-2 km) due to ongoing work on several structures in this alignment.
In this package, the alignment is very uneven, so many structures are being built to smoothen the road. Work on these structures is ongoing, with bitumen laying continuing on the completed sections. Near Amba village, work on structures is progressing, with bitumen being laid on the finished roads.
Next is the Limdi Interchange, which is being built on NH 48. The toll structure work on this interchange is complete, and bitumen laying is also complete on the main alignment, but the work on the entry and exit roads is still pending.
As we pass through the interchange, NH 56 crosses nearby, and bridge work over the NH 56 intersection is ongoing, with pier construction work taking place on one side of the bridge. Moving ahead, wayside amenities are planned but no work has started on this location as of now.
As we approach Dhara Dungri village, bridge work over a small river is in progress, with pier construction ongoing. Further ahead, bitumen laying on the road is mostly complete until Gultora village (Jhalod taluka of Dohad dist.), where a viaduct is being built, and girder erection work is underway. Moving ahead, bitumen laying is complete on most of the part, with finishing work left.
Near the Chakliya-Dahod road crossing, an overpass is being built with the pier cap complete, but girder erection is pending. Just before the Anas river, Package 26 ends. Compared to other packages in the Vadodara to Dahod segment of the expressway, not much work has been completed on Package 26. This can be attributed to the uneven alignment and the large number of structures being built to make the road steady and even.
In conclusion, looking at the pending work left on this package, it will take at least one more year to be ready. This was the last package in Gujarat, and after the Anas river, the expressway is completed all the way to the Mukundra Hills tunnel in Rajasthan. DeshGujarat
Related Stories
Progress update of Vadodara - Dahod - MP Border section of Delhi-Mumbai Expressway
Package-wise update on work in progress on Gujarat portion of Delhi-Mumbai Expressway
Update of work in progress on Godhra-Dahod section of Delhi-Mumbai Expressway
Update on work in progress on Vadodara-Godhra section of Delhi-Mumbai Expressway
Recent Stories
- Ahmedabad Traffic Police launch drive against car owners with aftermarket LED headlights
- Ahmedabad Crime Branch nabs 5 absconding accused in Khyati hospital case
- Namo Lakshmi Yojana: Financial aid of over ₹138 crore disbursed to 10 lakh girls
- Mahesh Langa gets anticipatory bail in Rs. 28 lakh cheating case
- Indore-Dahod rail line project: Earthwork completed till Gunavad; completion expected by 2026
- ED searches in 3 states including Gujarat in ‘Fairplay’ case; assets worth Rs. 219.66 cr attached
- Valsad college girl rape and murder case detected; Accused turns out to be a serial killer