First work order Ahmedabad Metro rail project awarded
February 04, 2015
Ahmedabad, DeshGujarat
First work order Ahmedabad Metro rail project has been awarded. Rs. 278 crore work order awarded today involves Vastral-Apparel park stretch of Metro rail project construction of which is likely to start by March 2015.
Gujarat government arm Metrolink Express for Gandhinagar and Ahmedabad – MEGA company had invited tender for “construction of Elevated Viaduct from Vastral Gam to Apparel Park upto Ramp Start in Reach R-1 (Excluding the portions of Metro Rail Stations) including construction of viaduct for portion leading upto interface location of Metro Depot (East West Corridor) in Khokhra area from diverting point near Apparel Park Metro Rail Station”.
Vastral village – Apparel Park(Khokhra) stretch is 6 km long. It is part of the first phase of Metro rail project connecting Vastral gam and Thaltej gam in east-west direction.
The tender was made public on 20 October. It was only for construction of elevated viaduct on 6 km stretch. There will be total 7 Metro stations on 7.5 km route, construction of which will be covered in separate tender. Distance between two stations will be around 1200-1500 meter.
A note issued today to media by MEGA said: Estimated expenditure of civil work of a 6 km elevated corridor between Vatral to Apparel park was Rs. 266 crore. MEGA had invited tenders in October 2014. From all over the nation, total 9 companies had participated in this tender process. Technical bid was opened on 18 December last year. After scrutiny of technical qualification, 4 agencies were found successful. Later, financial bid was opened on 22 January 2015. After a scrutiny process, Mumbai based J. Kumar Infracon Projects ltd was found lowest-1(L1) in its offer with Rs. 278 crore bid. L&T, Simplex, Soma companies stayed at second, third and fourth position respectively. In a meeting of the board of directors held on 31 January 2015, J.Kumar Infraprojcts ltd was issued a letter of acceptance. The work will begin by the end of this month and will be completed in 27 months period.
MEGA plans to operate 4-6 coaches to begin with at 45-100 km/hour speed.
About phase-1
Metro rail North-South corridor(APMC market to Motera stadium) and East-West corridor(Thaltej village to Vastral) are part of Metro rail project phase-1.
Phase-1 route length is 35.956 km, of which 29.621 will be over surface while 6.355 km route will be underground. 28 stations will be over the surface and 4 stations will be underground.
North-South corridor will begin at Motera stadium. It will pass through Sabarmati police station, power house, RTO over-bridge, Ranip 132 ring road, Ranip cross road, Vadaj AMTS bus-stand, Usmanpura, Ashram road, New Gandhigram, Madalpur, Paldi, Anjli, Vasna and end at APMC.
East-West corridor will begin at Thaltej village and pass through Doordarshan kendr, Gurukul road, Gujarat University, Commerce six roads, Stadium, Ashram road, Shahpur, Ghikanta, Kalupur railway station, Kankaria east(Gomtipur), Apparel park, Amraiwadi, Rabari colony, Vastral, Nirat char rasta and Vastral village, which will be the last station.
The project above is likely to be completed in year 2018.
© Copyright DeshGujarat. All rights reserved. Republication or redistribution of any DeshGujarat content, including by framing or similar means, is expressly prohibited without their prior written consent.
Related Stories
First Metro train in Ahmedabad to run in January 2019, ongoing works to complete by December 2019: Rupani
Gujarat Chief Minister reviews Ahmedabad Metro Rail project progress
Specifications and ridership projections of Ahmedabad Metro train
Gujarat CM launches works for North-South corridor (Line-2) of Ahmedabad Metro
Ahmedabad Metro underground section to be completed in 27 months:CMD
Metro rail project: MEGA converted to SPV, ten Directors appointed
First 6 km works of Ahmedabad Metro to complete by September 2016:CM
Watch invitation card of stone laying for Ahmedabad Metro project
'Rs 472.29 crore spent on Ahmedabad Metro rail project in last 2 years'
Recent Stories
- Cyclists hit by overspeeding SUV on SG Highway based overbridge
- Gujarat govt to form AI Task Force
- Khambhat police book 31 for attacking police personnel
- BJP wins Vav assembly by-election in Banaskantha
- Progress update of Vadodara - Dahod - MP Border section of Delhi-Mumbai Expressway
- Thaltej Gam Metro Station ready; likely to open in December 2024
- Over 5 lakh tourists visit Rani ki Vav in Gujarat in two years