Salinity control cost up by 355% due to delays in action: CAG report on Gujarat
March 29, 2018
Gandhinagar: The report of the Comptroller and Auditor General (CAG) tabled in Gujarat Assembly on Wednesday has blamed exceptional delays in implementation of salinity ingress prevention programmes, which has led to cost escalation of 355% and resulted into further aggravation of the problem. The delays listed out include limited or no action on establishment of a trialcum-demonstration (TCD) farm, coastal land reclamation, gully plugging or building small dams and the slow pace of afforestation.
The CAG report reads:
The audit observed that except in case of check dams and recharge wells, progress on works was very slow even 25 to 39 years after the acceptance of the report of the HLC (high level committee) by the Gujarat government. Even the plan document, detailed project report and budget estimates were not prepared for these activities. Against the original cost of Rs 789.12 crore estimated by the HLCs, expenditure of Rs 1,045.65 crore was incurred up to March 2017. For the remaining works, the estimate was revised to Rs 2,544.79 crore. Thus, due to the delay in implementation of the recommended works, the cost of the scheme escalated by 355%. The groundwater legislation recommended by the HLC in 1978 has not been enacted till March 2017.
In respect of three works of tidal regulators (TR) it was noticed that the works were awarded without acquisition of the required land, resulting in the works remaining incomplete till March 2017 and expenditure of Rs 11.1 crore rendered unfruitful.
The HLCs suggested stopping of tidal ingress into the land by constructing TRs near the mouths of the rivers to seal them. However, it was noticed that six TRs were constructed beyond the tidal reach of sea water. Hence, the sea water would still intrude and the Bandharas would not serve the purpose of prevention of sea water ingress but would only act as a check dam for creation of a sweetwater reservoir.
There was wasteful expenditure of Rs 25.77 crore on bandharas because of land acquisition hurdles. The CAG observed, “The groundwater quality in salinity affected areas are chemically analysed on the basis of total dissolved solids (TDS) and the ratio of chloride to carbonate plus bi-carbonate content in the water. Compared to May 2012, in all the number of wells under the fresh water category have reduced in May 2016.
Related Stories
CAG report slams Gujarat govt for neglect of the fisheries sector
1978 legislation not enacted: CAG slams Gujarat govt over lack of action for groundwater conservation
CAG points out number of shortcomings in lion conservation efforts in Gujarat
CAG report tabled in Gujarat Assembly, Congress objects to its tabling on last day of session
Recent Stories
- Cyclists hit by overspeeding SUV on SG Highway based overbridge
- Gujarat govt to form AI Task Force
- Khambhat police book 31 for attacking police personnel
- BJP wins Vav assembly by-election in Banaskantha
- Progress update of Vadodara - Dahod - MP Border section of Delhi-Mumbai Expressway
- Thaltej Gam Metro Station ready; likely to open in December 2024
- Over 5 lakh tourists visit Rani ki Vav in Gujarat in two years