Surat Outer Ring Road Phase-2 construction likely to commence after Diwali this year
June 28, 2024
Surat: Surat will soon witness the commencement of Phase-2 construction of the Outer Ring Road. This phase aims to add 10.45 km to the existing road with an estimated cost of Rs 473.37 crore. The tender process for the project’s second phase will soon be completed, with construction expected to commence after Diwali or in January 2025, it is learnt.
Phase-1 Progress and Details
The estimated cost for this phase is Rs 486.44 crore. This phase covers an area of 17.32 km and is divided into packages. Package-1 includes ongoing infrastructure construction such as the Kosad-Bharthana railway overbridge, an overbridge from Valak village to Surat Kamrej road, a vehicle underpass, and a Y junction near Gadhpur road. Completion of this work will complete the entire work of phase-1.
Phase-2 Tender Process and Project Details
The tender process for Phase-2, covering 10.45 km, is nearing completion. The estimated cost of this phase is Rs 473.37 crore. This phase will include the construction of railway overbridge, flyover bridge, underpass, etc. Phase-2 of the outer ring road will connect Niyol, Dindoli, Kharvasa, Khambhasla, Saniya Kanade, Pardi Kanade, Bhanodra, and Sachin. Additionally, connectivity will extend to Surat-Kadodara Road, Dindoli-Palsana, Dindoli-Chalthan, Dindoli-Bhestan, and Sachin-Eklera roads.
Inclusion of State and National Highways
- The outer ring road spans 66.77 km and includes state and national highways.
- It incorporates a 21 km existing National Highway between Hazira and Sachin.
- There is a 13 km State Highway between Ichhapor and Saroli within the project.
- Construction of a 27 km ring road segment between Variyav and Sachin is currently ongoing.
- Additionally, 5 km of municipal roads are part of the overall development.
Land Acquisition and Project Scope
Plans are underway to acquire necessary land for Phase-2 from villages including Niyol, Dindoli, Kharvasa, Khambhasla, Saniya Kanade, Pardi Kanade, Bhanodra, and Sachin. With an estimated total project cost exceeding Rs 960 crore, the Surat Outer Ring Road project aims to enhance connectivity and reduce travel time across Surat and its surrounding regions. DeshGujarat
Related Stories
Surat Outer Ring Road Second Phase to involve Rs. 387 crore works
Surat Outer Ring Road Second Phase to See Rs 387 crore worth roads and bridges works
Surat: SMC defers reopening of Ring Road flyover bridge to end-June
Surat gets longest river bridge which also completes the Ring Road
SPV to implement the Surat Outer Ring Road project
Recent Stories
- Fire breaks out at ISKON Platinum residential high-rise in Bopal
- 4.2 magnitude tremor felt in parts of North Gujarat
- HM Amit Shah likely to visit Gujarat on Nov 18-19
- University of Wollongong India opens India campus in GIFT City
- Children’s Day: Reliance Foundation’s annual ‘Kahani Kala Khushi’ begins
- NHSRCL shares progress on construction of bullet train stations in Gujarat
- MICA student stabbing accused cop sent to 10-day remand until Nov 25