150 MW Gujarat solar project of NTPC becomes fully operational
May 02, 2025
New Delhi: NTPC Green Energy Limited on Friday announced that its subsidiary, NTPC Renewable Energy, has achieved full commercial operation of its 150 MW Gujarat Solar PV project. The milestone was confirmed following a certification issued by the Gujarat Energy Development Agency (GEDA) on April 30, 2025.
According to the company, the final phase of 60 MW capacity began commercial operations on April 16, 2025. The earlier phases—60 MW and 30 MW—were commissioned on July 29, 2024, and December 11, 2024, respectively. The project is part of the 500 MW solar capacity awarded under the GUVNL (Phase XII) tender and marks a significant step in India’s renewable energy expansion. DeshGujarat
Recent Stories
- Unseasonal rain, dust storms hit parts of Gujarat
- Gujarat Govt to Amend Disturbed Areas Act, Plans to Rename ‘Disturbed Areas’ as ‘Specified Areas’
- Gujarat HC Rejects Plea to Quash FIR Against Gajera Brothers in ₹1,928 Crore Cheating Case
- Centre Designates Special NIA Court in Ahmedabad for Trial of Terror Cases
- Unseasonal Rain, Hailstorm Hit Jamnagar’s Lalpur