Ahmedabad Railway Station Revamp: Platforms 4-7 to Get Modern Concourse in 120 Days

Ahmedabad Railway Station Revamp: Platforms 4-7 to Get Modern Concourse in 120 Days

Ahmedabad: Passengers using platforms 4, 5, 6 and 7 at Kalupur Junction in the city are set to get improved facilities and a modern concourse, with redevelopment work expected to be completed within 120 days.

The project aims to improve passenger movement and the overall travel experience while ensuring train operations continue uninterrupted at one of the city’s busiest railway stations.

Ahmedabad Divisional Railway Manager (DRM) Ved Prakash, along with officials from the Rail Land Development Authority (RLDA), railway departments and the construction agency, inspected the site on Friday to review progress and address challenges.

The review covered construction progress, technical issues, manpower and machinery availability, material supply, traffic and power blocks, and coordination among agencies. The construction plan includes 457 piles, 108 pile caps and 213 pedestals for platforms 4/5 and 6/7, along with the fabrication and erection of around 6,400 tonnes of structural steel.

The project involves pile foundations, pile caps and pedestals, ballast-less track (BLT) construction and structural work for the concourse. Officials have been instructed to ensure adequate manpower, machinery and material supplies to meet the completion deadline. DeshGujarat