Articles tagged under: Delhi-Mumbai Express way

Delhi-Mumbai Expressway: Update on work in progress on Vadodara-Surat section

June 20, 2025
Delhi-Mumbai Expressway: Update on work in progress on Vadodara-Surat section

Vadodara: As work progresses steadily on the 1,386-km, eight-lane Delhi-Mumbai Expressway, commuters continue to await the opening of the crucial Vadodara–Surat section, which is expected to bring major relief to travelers in South and Central Gujarat. This stretch has been divided into six packages. Among these, Packages 1 to 3, connecting Vadodara to Bharuch, are already operational. As per the National Highways Authority of India (NHAI) data as of April 1, 2025, Packages 4 (Manubar to Ankl...Read More

Delhi-Mumbai Expressway in Gujarat: Section-wise progress update

May 31, 2025
Delhi-Mumbai Expressway in Gujarat: Section-wise progress update

Vadodara: The construction of the 1,386 km-long, eight-lane Delhi-Mumbai Expressway is advancing swiftly. To facilitate efficient progress, the project has been divided into multiple sections and packages. This report offers a detailed package-wise update on the 426 km stretch of the expressway passing through Gujarat. In Gujarat, the expressway falls under two sections, namely Delhi to Vadodara and Vadodara to Virar. The Delhi to Vadodara stretch consists of 31 packages in total, with packages...Read More

Delhi Mumbai Expressway: Stalled for over 2 years, work begins on 1.5 km stretch in Ankleshwar

May 17, 2025
Delhi Mumbai Expressway: Stalled for over 2 years, work begins on 1.5 km stretch in Ankleshwar

Ankleshwar: The construction work on the Delhi-Mumbai Expressway between Old Diwa and Punagam in Ankleshwar taluka resumed on Friday under police protection despite farmer protests. However, farmers from the expected villages did not turn up in large numbers to oppose the work. The expressway work passing through villages of Ankleshwar taluka, connecting Vadodara to Mumbai, had been partially stalled due to disputes over compensation with farmers. Today, the administration restarted the constru...Read More

1,156 km out of 1,386 km of Delhi-Mumbai Expressway complete: Centre in Rajya Sabha

April 03, 2025
1,156 km out of 1,386 km of Delhi-Mumbai Expressway complete: Centre in Rajya Sabha

New Delhi: As of February 2025, a total length of 1,156 km out of 1,386 km of the Delhi-Mumbai Expressway has been completed across States. Out of this, 756 km has been operationalised. Initially, there were delays in the project due to slow progress by the contractors, force majeure issues, land acquisition issues. The Government is taking all relevant steps to ensure the timely completion of the remaining length. The final cost of the project can only be ascertained post completion of t...Read More

Toll Rate Hike on NE-4 Vadodara-Bharuch Section of Delhi-Mumbai Expressway

April 01, 2025
Toll Rate Hike on NE-4 Vadodara-Bharuch Section of Delhi-Mumbai Expressway

Vadodara: The revised toll rates for the Vadodara-Bharuch section of the Delhi-Mumbai Expressway have come into effect today, April 1, 2025. The National Highway Authority of India (NHAI) has announced the updated toll fees across the highways in the county as part of the annual revision. Motorists traveling along the Vadodara-Bharuch stretch (spanning approximately 91.474 km from Km 844.667 to Km 936.141) will now be subject to higher toll charges at various toll plazas, including Dodaka, Faja...Read More

Farmers Disrupt Mumbai-Vadodara Expressway Construction in Surat District Over Blocked Field Access

March 25, 2025
Farmers Disrupt Mumbai-Vadodara Expressway Construction in Surat District Over Blocked Field Access

Surat: Construction of the Mumbai-Vadodara Expressway, passing through the Bardoli, Palsana, and Kamrej talukas of Surat district, has been halted by protesting farmers who claim their access to agricultural fields has been blocked. Some farmers claimed that the expressway construction has reportedly cut off access roads to numerous farms, causing hardship for farmers who need to transport sugarcane, vegetables, and other produce. Despite repeated appeals to the National Highway Authority of I...Read More

Delhi-Mumbai Expressway: Progress update on Navsari-Surat Package 7 of Vadodara-Virar section

February 22, 2025
Delhi-Mumbai Expressway: Progress update on Navsari-Surat Package 7 of Vadodara-Virar section

Navsari: The construction of the eight-lane Delhi-Mumbai Expressway is progressing in two sections, one of which is the Vadodara-Virar section. This Vadodara-Virar section consists of 10 packages, and Package 7 connects the Kharel Interchange (near Gandeva) in Navsari to the Ena Interchange in Surat district. Package 7 is approximately 28 kilometers long, and IRB is handling its construction. Today, we bring you a ground report on this package based on vloggers’ insights and on-site footage. ...Read More

Hold-up in some Gujarat sections delays Delhi-Mumbai Expressway completion; likely opening in 2027

February 14, 2025
Hold-up in some Gujarat sections delays Delhi-Mumbai Expressway completion; likely opening in 2027

New Delhi: The completion of the Delhi-Mumbai Expressway, which was initially scheduled for October 2024, is now likely to be delayed by around two years. According to a report, the delay is due to the incomplete construction of six sections of the expressway, including three packages in Gujarat covering a total of 87 km. It is learned that one 35-km stretch has seen no progress, while work on the other two sections stands at 7% and 35%, respectively. The 1,386-km-long, eight-lane Delhi-Mumba...Read More

Ground report on the progress of Delhi-Mumbai Expressway’s Ena-Kim Package in Surat

February 07, 2025
Ground report on the progress of Delhi-Mumbai Expressway’s Ena-Kim Package in Surat

Surat: The 1,386 km-long, eight-lane Delhi-Mumbai Expressway is being built in two sections, i.e., Delhi-Vadodara and Vadodara-Virar. In this Vadodara-Virar section, Package 6 connects the Ena Interchange (at NH 53) to the Kim Interchange (NH 48), both falling in the Surat district. This package, built by GR Ena Kim Expressway Private Limited, received the Provisional Completion Certificate in January, meaning it is almost ready for public use. However, in this package, two major works are pendi...Read More

Why Package 26 of Delhi-Vadodara section of Delhi-Mumbai Expressway is difficult to construct?

February 01, 2025
Why Package 26 of Delhi-Vadodara section of Delhi-Mumbai Expressway is difficult to construct?

Dahod: The Delhi-Mumbai Expressway construction is ongoing in Gujarat, with packages 26 to 31 of this project falling under the Dahod-Vadodara segment. The first package that falls in Gujarat is Package 26, which starts from Bhimpura Village in Dahod and ends near the Anas River at the state border between Gujarat and Madhya Pradesh. This package is being built by Atlas Construction at a cost of Rs. 1,971.36 crore. As of now, only 54.21% of the financial progress has been reported on this packag...Read More