Come November, platforms of Ahmedabad railway station likely to close in phased manner for redevelopment
September 09, 2024
Kalupur: With the ongoing redevelopment of Kalupur Railway Station in the city, platforms No. 1 to 9 will be closed for operations in four phases starting from November this year. During this time, the train operations from Kalupur station will be shifted to other railway stations located in the city, a local newspaper report claimed.
Currently, many trains are operating from Sabarmati and Gandhinagar Capital stations, and preparations are underway to shift additional trains to Sabarmati, Asarwa, Maninagar, and Vatwa stations. The stoppage time for trains coming from Saurashtra, Bhuj, and Rajasthan will also be reduced during the phased platform closure. Some trains are expected to have their stoppage moved to Maninagar station.
Maintenance work for trains in Ahmedabad will also be relocated. Operations for loading parcels from Ahmedabad onto trains arriving from Saurashtra, Bhuj, and Rajasthan will be shifted to other stations, with official announcements expected in the coming days.
Tentative periods of time the platforms will be closed:
• Platform No. 7, 8, 9: Closed from November 15 to February 15
• Platform No. 5, 6: Closed from February 15 to May 15
• Platform No. 1, 2: Closed from May 15 to August 12, 2025
• Platform No. 3, 4: Closed from August 12 to November 10, 2025
Recent Stories
- Diwali Food Safety Drive: AMC Seals Two Units, Fines Four Outlets ₹40,000
- HDFC Bank Gets Govt Nod to Offer Deposits Under Capital Gains Accounts Scheme
- GSSSB Announces Recruitment for 1,237 Class-3 Posts; Applications Open on November 5
- AMC to Hike Parking Fees; Proposed New Rates Here
- Mumbai Mayor Ritu Tawde Meets Gujarat CM Bhupendra Patel
- Holiday Inn Resort to Come Up in Sasan Gir