Bullet Train: Casting yards in Vadodara, Vapi complete 1,000 Full Span Box Girders each
September 20, 2024
Vapi: In yet another breakthrough in the Mumbai-Ahmedabad Bullet Train project, two casting yards located in Vadodara and Vapi, Gujarat, have completed the casting of 1,000 Full Span Box Girders each for the viaduct of the project.
According to the press release from the National High-Speed Rail Corporation Limited, Out of 352 km of alignment in Gujarat and DNH, 290 km of viaduct will be constructed through full span launching (FSLM) and the remaining alignment will be majorly through segmental launching, 17 steel bridges, 8 stations, 350m long tunnel and other civil structures.
Full span girders used in viaduct construction of Bullet Train project are 40 meters in length and weighs 970 MT.
Details of full span launching girders in Gujarat & DNH:
| Scope: Total no. of full span girders | No. of FSLM girders cast | No. of FSLM girders launched to make viaduct |
|---|---|---|
| 7277 (290 km) | 5169 (207 km) | 4651 (186 km) |
The casting yards are well planned dedicated factories equipped with Make in India machinery like straddle carriers, full span launching gantry, girder transporter, bridge gantry and full span girder casting moulds.
At present, 213 km of viaduct has been completed in Gujarat which includes both SBS (Span by Span) and FLSM launching.
Recent Stories
- Diwali Food Safety Drive: AMC Seals Two Units, Fines Four Outlets ₹40,000
- HDFC Bank Gets Govt Nod to Offer Deposits Under Capital Gains Accounts Scheme
- GSSSB Announces Recruitment for 1,237 Class-3 Posts; Applications Open on November 5
- AMC to Hike Parking Fees; Proposed New Rates Here
- Mumbai Mayor Ritu Tawde Meets Gujarat CM Bhupendra Patel
- Holiday Inn Resort to Come Up in Sasan Gir
