Surat: Surat Municipal Commissioner Shalini Agrawal today inspected the ongoing works under the Dumas Seafront Development Project, a major coastal tourism initiative aimed at enhancing recreational facilities and showcasing the natural beauty of the spot for both domestic and international visitors. The Commissioner imposed a penalty of ₹5 lakh on the contractor.
The project covers 102 hectares along the Dumas coastline and includes the development of tourist facilities across a 5.5 km stretch of the seashore. As part of Zone-1, spread over 12.86 hectares, capital works worth ₹244 crore are currently under rapid progress.
The development includes several key attractions such as a surface parking facility, multi-level car parking (MLCP) building, four-wheeler and two-wheeler parking areas, cycling track, promenade, walkway, erosion protection wall, amenities building, yoga ground, event plaza, INS Surat model ship installation, marine-themed sculptures, and a convenience plaza.
As part of smart monitoring under the 12.86-hectare zone, the MLCP building will serve as a central control room for real-time surveillance and management. This will include:
-CCTV camera network
-Digital displays
-NBS Trail system
-Integrated water supply network
-STP inflow/outflow systems
-Recharge bore facilities
-Monitoring and security systems
-Tourist emergency response
-Disaster management plan
-Digital management and supervision tools
During her visit, the Commissioner reviewed completed works such as the surface parking, yoga ground, promenade area, and the mechanised parking system inside the MLCP building. She instructed officials and contractors to expedite all pending works, including horticulture, with utmost priority.
However, action was also taken for non-compliance. Since the executing contractor failed to install adequate measures to prevent dust pollution, the Commissioner imposed a penalty of ₹5 lakh on the contractor.
The Dumas Seafront Project aims to transform the spot into a vibrant coastal tourism destination, offering modern amenities while preserving its natural charm.
Related Stories
Dumas Sea-Face Project Phase 1 Likely to Open on March 8
Dumas Sea Face Project Opening Delayed; Surat Civic Body Warns Contractor
Zone 1 of Dumas Sea Face Development Project 75% complete; likely to open in Dec
Phase 1 of Dumas Sea Face Development Project likely to be ready by year-end
Replica of INS Surat to come up at Dumas Sea Face
Recent Stories
- 1,600+ Police Personnel Deployed for Transmission Line Works in Kutch, Dwarka Over Two Years
- Dr. Rizvan Kadri's book 'Sabarmati Navigation: 1894's Unfulfilled Blueprint' Launched in Ahmedabad
- CJI Surya Kant to be Chief Guest at NFSU Convocation in Gandhinagar; To Launch IDDRC
- Traffic Diversions Announced in Ahmedabad for Bhadrakali Mataji Nagar Yatra
- Ahmedabad's Latest New Metro Station to Open in Couple of Months