Ahmedabad civic body okays Rs 21.55 crore plan for repairs of three key bridges
October 22, 2025
Ahmedabad: The standing committee of the Ahmedabad Municipal Corporation (AMC) has approved a Rs 21.55 crore plan for the maintenance of three of the city’s aging bridges — Gandhi Bridge, Sardar Bridge, and Parikshitlal Majmudar Bridge.
The approved work includes lifting 89 spans — 38 of Gandhi Bridge, 48 of Sardar Bridge, and 3 of Parikshitlal Majmudar Bridge — and replacing the elastomeric bearings. Following the Gambhira Bridge tragedy on July 9, the state government instructed inspections of all city bridges and mandated necessary repairs. An AMC official said that due to the absence of a current rate tender, it was decided to expand the Ellis Bridge contractor’s scope to include these three bridges.
In the same meeting, the committee also approved increasing the Ellis Bridge restoration cost from Rs 26.88 crore to Rs 42.90 crore, sanctioning an additional Rs 16 crore.
The contractor has already installed new steel structural plates and seismic arresters on Gandhi Bridge, completing span lifting and bearing replacement without disrupting traffic. Bearing replacement work for Sardar Bridge and Parikshitlal Majmudar Bridge is expected to be carried out in the coming days. DeshGujarat
Recent Stories
- Gujarat HC CJ Sunita Agarwal elevated to SC; Senior Most Justice Pathak Likely Acting Chief Justice
- Surendranagar Police Raid Gym, Recover 100s of Photos and Videos of Hindu Women
- Sabarmati Riverfront Phase-II: 82% Work Completed, Entire Phase Expected by December 2027
- Gujarat Govt Buildings Have 95 MW Rooftop Solar Capacity, Another 65 MW Planned This Year
- Surat Airport Expands Use of Renewable Energy
- Bullet Train Bridge over Sabarmati River in Ahmedabad completed