Central Environment and Forest ministry has issued a show cause notice to M/s Nirma Ltd. for permanent suspension of work and revocation of the environmental clearance regarding the cement plant, coke oven plant(1.5 LTPA) and captive power plant(50 MW) near village Padhiarka, Taluka Mahuva, District Bhavnagar under section 5 of the Environment(Protection) Act, 1986.

The ministry in its notice to Nirma signed by Scientist ‘F’ Dr. P.L.Ahujarai said:”In view of the conclusions of the EAC(Experts Appraisal Committee) and the fragile nature as also the importance of avoiding any further damage to the wetland, you are hereby directed to stop the implementation, including construction work, of the project with immediate effect and until further orders.”

The ministry has directed Nirma company to show cause as to why the environmental clearance accorded to the project should not be revoked and the stoppage of the work not be made permanent.

The ministry has asked Nirma company that in case the company desires any personal hearing, it can be on 16th or 17th March, 2011, provided the response is received at least one day before that date.
Full draft of order against Nirma